Sprint is 2 week and 40-stories

The name of the pictureThe name of the pictureThe name of the pictureClash Royale CLAN TAG#URR8PPP












9















Question for QA- What you are doing if your current sprint is 2 week and you have 20 stories, suddenly PO added more 20 stories how you handle this situation..?










share|improve this question

















  • 6





    If the Product Owner is assigning stories to the Development Team or directly adding stories the Sprint Backlog, then whatever you're doing is not Scrum.

    – Todd A. Jacobs
    Feb 26 at 14:51
















9















Question for QA- What you are doing if your current sprint is 2 week and you have 20 stories, suddenly PO added more 20 stories how you handle this situation..?










share|improve this question

















  • 6





    If the Product Owner is assigning stories to the Development Team or directly adding stories the Sprint Backlog, then whatever you're doing is not Scrum.

    – Todd A. Jacobs
    Feb 26 at 14:51














9












9








9








Question for QA- What you are doing if your current sprint is 2 week and you have 20 stories, suddenly PO added more 20 stories how you handle this situation..?










share|improve this question














Question for QA- What you are doing if your current sprint is 2 week and you have 20 stories, suddenly PO added more 20 stories how you handle this situation..?







agile sprint quality-management agile-coach sprint-review






share|improve this question













share|improve this question











share|improve this question




share|improve this question










asked Feb 26 at 8:04









user28692user28692

463




463







  • 6





    If the Product Owner is assigning stories to the Development Team or directly adding stories the Sprint Backlog, then whatever you're doing is not Scrum.

    – Todd A. Jacobs
    Feb 26 at 14:51













  • 6





    If the Product Owner is assigning stories to the Development Team or directly adding stories the Sprint Backlog, then whatever you're doing is not Scrum.

    – Todd A. Jacobs
    Feb 26 at 14:51








6




6





If the Product Owner is assigning stories to the Development Team or directly adding stories the Sprint Backlog, then whatever you're doing is not Scrum.

– Todd A. Jacobs
Feb 26 at 14:51






If the Product Owner is assigning stories to the Development Team or directly adding stories the Sprint Backlog, then whatever you're doing is not Scrum.

– Todd A. Jacobs
Feb 26 at 14:51











2 Answers
2






active

oldest

votes


















13














If you are following Scrum as defined in the Scrum Guide, the Product Owner cannot simply add stories to the Sprint Backlog. The Sprint Backlog, which is created as Sprint Planning as a negotiation between the Product Owner and Development Team while considering past performance and forecast capacity, is owned exclusively by the Development Team.



If work comes in and it is a higher priority, there needs to be a discussion between the Product Owner and the Development Team on how to adjust the Sprint to balance the higher priority work with the remaining time and capacity of the Development Team. If the Sprint Goal is obsolete and the work that the team has been working on is no longer relevant or valuable, cancelling the Sprint is an option. If there are multiple Scrum Teams involved, dependencies must also be considered. The Scrum Master can facilitate any discussions or decisions made, including escalation beyond the Scrum Team if necessary.



Going back to the Scrum Values, the Development Team needs to have the courage and openness to push back against the Product Owner and protect their time. Going back all the way to the principles behind the Manifesto for Agile Software Development, development needs to be sustainable and done with a pace that can be held indefinitely, with continuous attention to technical excellence. Overloading Sprints or forcing the team is not collaborative and introduces a lot of risk and pain to an effort.






share|improve this answer






























    1














    is the 20 old stories represent a release? if yes there is a real problem at the business vision, where that the 20+ stories will completely lead to another product and how these extra stories were added it should be a collaborative process (PO with team), you have to re-estimate the stories, re-planning the release and the iteration, some people make the iteration time dynamic so you can extend it from 2 up to 4 weeks according to the PO business values

    in Scrum it is so important that all team members sit with PO in "Stories workshop" with "brainstorm" term to gathering all stories as possible this lead to good estimation for release, in your situation you must collaboratively re-planning the release(story workshop then estimate then prioritize and re-set the sprint time, finally assign the user stories in iteration according to the team velocity)






    share|improve this answer






















      Your Answer








      StackExchange.ready(function()
      var channelOptions =
      tags: "".split(" "),
      id: "208"
      ;
      initTagRenderer("".split(" "), "".split(" "), channelOptions);

      StackExchange.using("externalEditor", function()
      // Have to fire editor after snippets, if snippets enabled
      if (StackExchange.settings.snippets.snippetsEnabled)
      StackExchange.using("snippets", function()
      createEditor();
      );

      else
      createEditor();

      );

      function createEditor()
      StackExchange.prepareEditor(
      heartbeatType: 'answer',
      autoActivateHeartbeat: false,
      convertImagesToLinks: false,
      noModals: true,
      showLowRepImageUploadWarning: true,
      reputationToPostImages: null,
      bindNavPrevention: true,
      postfix: "",
      imageUploader:
      brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
      contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
      allowUrls: true
      ,
      noCode: true, onDemand: true,
      discardSelector: ".discard-answer"
      ,immediatelyShowMarkdownHelp:true
      );



      );













      draft saved

      draft discarded


















      StackExchange.ready(
      function ()
      StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25891%2fsprint-is-2-week-and-40-stories%23new-answer', 'question_page');

      );

      Post as a guest















      Required, but never shown

























      2 Answers
      2






      active

      oldest

      votes








      2 Answers
      2






      active

      oldest

      votes









      active

      oldest

      votes






      active

      oldest

      votes









      13














      If you are following Scrum as defined in the Scrum Guide, the Product Owner cannot simply add stories to the Sprint Backlog. The Sprint Backlog, which is created as Sprint Planning as a negotiation between the Product Owner and Development Team while considering past performance and forecast capacity, is owned exclusively by the Development Team.



      If work comes in and it is a higher priority, there needs to be a discussion between the Product Owner and the Development Team on how to adjust the Sprint to balance the higher priority work with the remaining time and capacity of the Development Team. If the Sprint Goal is obsolete and the work that the team has been working on is no longer relevant or valuable, cancelling the Sprint is an option. If there are multiple Scrum Teams involved, dependencies must also be considered. The Scrum Master can facilitate any discussions or decisions made, including escalation beyond the Scrum Team if necessary.



      Going back to the Scrum Values, the Development Team needs to have the courage and openness to push back against the Product Owner and protect their time. Going back all the way to the principles behind the Manifesto for Agile Software Development, development needs to be sustainable and done with a pace that can be held indefinitely, with continuous attention to technical excellence. Overloading Sprints or forcing the team is not collaborative and introduces a lot of risk and pain to an effort.






      share|improve this answer



























        13














        If you are following Scrum as defined in the Scrum Guide, the Product Owner cannot simply add stories to the Sprint Backlog. The Sprint Backlog, which is created as Sprint Planning as a negotiation between the Product Owner and Development Team while considering past performance and forecast capacity, is owned exclusively by the Development Team.



        If work comes in and it is a higher priority, there needs to be a discussion between the Product Owner and the Development Team on how to adjust the Sprint to balance the higher priority work with the remaining time and capacity of the Development Team. If the Sprint Goal is obsolete and the work that the team has been working on is no longer relevant or valuable, cancelling the Sprint is an option. If there are multiple Scrum Teams involved, dependencies must also be considered. The Scrum Master can facilitate any discussions or decisions made, including escalation beyond the Scrum Team if necessary.



        Going back to the Scrum Values, the Development Team needs to have the courage and openness to push back against the Product Owner and protect their time. Going back all the way to the principles behind the Manifesto for Agile Software Development, development needs to be sustainable and done with a pace that can be held indefinitely, with continuous attention to technical excellence. Overloading Sprints or forcing the team is not collaborative and introduces a lot of risk and pain to an effort.






        share|improve this answer

























          13












          13








          13







          If you are following Scrum as defined in the Scrum Guide, the Product Owner cannot simply add stories to the Sprint Backlog. The Sprint Backlog, which is created as Sprint Planning as a negotiation between the Product Owner and Development Team while considering past performance and forecast capacity, is owned exclusively by the Development Team.



          If work comes in and it is a higher priority, there needs to be a discussion between the Product Owner and the Development Team on how to adjust the Sprint to balance the higher priority work with the remaining time and capacity of the Development Team. If the Sprint Goal is obsolete and the work that the team has been working on is no longer relevant or valuable, cancelling the Sprint is an option. If there are multiple Scrum Teams involved, dependencies must also be considered. The Scrum Master can facilitate any discussions or decisions made, including escalation beyond the Scrum Team if necessary.



          Going back to the Scrum Values, the Development Team needs to have the courage and openness to push back against the Product Owner and protect their time. Going back all the way to the principles behind the Manifesto for Agile Software Development, development needs to be sustainable and done with a pace that can be held indefinitely, with continuous attention to technical excellence. Overloading Sprints or forcing the team is not collaborative and introduces a lot of risk and pain to an effort.






          share|improve this answer













          If you are following Scrum as defined in the Scrum Guide, the Product Owner cannot simply add stories to the Sprint Backlog. The Sprint Backlog, which is created as Sprint Planning as a negotiation between the Product Owner and Development Team while considering past performance and forecast capacity, is owned exclusively by the Development Team.



          If work comes in and it is a higher priority, there needs to be a discussion between the Product Owner and the Development Team on how to adjust the Sprint to balance the higher priority work with the remaining time and capacity of the Development Team. If the Sprint Goal is obsolete and the work that the team has been working on is no longer relevant or valuable, cancelling the Sprint is an option. If there are multiple Scrum Teams involved, dependencies must also be considered. The Scrum Master can facilitate any discussions or decisions made, including escalation beyond the Scrum Team if necessary.



          Going back to the Scrum Values, the Development Team needs to have the courage and openness to push back against the Product Owner and protect their time. Going back all the way to the principles behind the Manifesto for Agile Software Development, development needs to be sustainable and done with a pace that can be held indefinitely, with continuous attention to technical excellence. Overloading Sprints or forcing the team is not collaborative and introduces a lot of risk and pain to an effort.







          share|improve this answer












          share|improve this answer



          share|improve this answer










          answered Feb 26 at 11:02









          Thomas OwensThomas Owens

          5,0761428




          5,0761428





















              1














              is the 20 old stories represent a release? if yes there is a real problem at the business vision, where that the 20+ stories will completely lead to another product and how these extra stories were added it should be a collaborative process (PO with team), you have to re-estimate the stories, re-planning the release and the iteration, some people make the iteration time dynamic so you can extend it from 2 up to 4 weeks according to the PO business values

              in Scrum it is so important that all team members sit with PO in "Stories workshop" with "brainstorm" term to gathering all stories as possible this lead to good estimation for release, in your situation you must collaboratively re-planning the release(story workshop then estimate then prioritize and re-set the sprint time, finally assign the user stories in iteration according to the team velocity)






              share|improve this answer



























                1














                is the 20 old stories represent a release? if yes there is a real problem at the business vision, where that the 20+ stories will completely lead to another product and how these extra stories were added it should be a collaborative process (PO with team), you have to re-estimate the stories, re-planning the release and the iteration, some people make the iteration time dynamic so you can extend it from 2 up to 4 weeks according to the PO business values

                in Scrum it is so important that all team members sit with PO in "Stories workshop" with "brainstorm" term to gathering all stories as possible this lead to good estimation for release, in your situation you must collaboratively re-planning the release(story workshop then estimate then prioritize and re-set the sprint time, finally assign the user stories in iteration according to the team velocity)






                share|improve this answer

























                  1












                  1








                  1







                  is the 20 old stories represent a release? if yes there is a real problem at the business vision, where that the 20+ stories will completely lead to another product and how these extra stories were added it should be a collaborative process (PO with team), you have to re-estimate the stories, re-planning the release and the iteration, some people make the iteration time dynamic so you can extend it from 2 up to 4 weeks according to the PO business values

                  in Scrum it is so important that all team members sit with PO in "Stories workshop" with "brainstorm" term to gathering all stories as possible this lead to good estimation for release, in your situation you must collaboratively re-planning the release(story workshop then estimate then prioritize and re-set the sprint time, finally assign the user stories in iteration according to the team velocity)






                  share|improve this answer













                  is the 20 old stories represent a release? if yes there is a real problem at the business vision, where that the 20+ stories will completely lead to another product and how these extra stories were added it should be a collaborative process (PO with team), you have to re-estimate the stories, re-planning the release and the iteration, some people make the iteration time dynamic so you can extend it from 2 up to 4 weeks according to the PO business values

                  in Scrum it is so important that all team members sit with PO in "Stories workshop" with "brainstorm" term to gathering all stories as possible this lead to good estimation for release, in your situation you must collaboratively re-planning the release(story workshop then estimate then prioritize and re-set the sprint time, finally assign the user stories in iteration according to the team velocity)







                  share|improve this answer












                  share|improve this answer



                  share|improve this answer










                  answered Feb 26 at 14:36









                  Mjd KassemMjd Kassem

                  638




                  638



























                      draft saved

                      draft discarded
















































                      Thanks for contributing an answer to Project Management Stack Exchange!


                      • Please be sure to answer the question. Provide details and share your research!

                      But avoid


                      • Asking for help, clarification, or responding to other answers.

                      • Making statements based on opinion; back them up with references or personal experience.

                      To learn more, see our tips on writing great answers.




                      draft saved


                      draft discarded














                      StackExchange.ready(
                      function ()
                      StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25891%2fsprint-is-2-week-and-40-stories%23new-answer', 'question_page');

                      );

                      Post as a guest















                      Required, but never shown





















































                      Required, but never shown














                      Required, but never shown












                      Required, but never shown







                      Required, but never shown

































                      Required, but never shown














                      Required, but never shown












                      Required, but never shown







                      Required, but never shown






                      Popular posts from this blog

                      How to check contact read email or not when send email to Individual?

                      Displaying single band from multi-band raster using QGIS

                      How many registers does an x86_64 CPU actually have?